How We Priced Out Our First Flip (and Where We Were Wrong)

October 20, 2026 · Real renovation and flip numbers, start to finish

How We Priced Out Our First Flip (and Where We Were Wrong)

Public domain, via Wikimedia Commons

The number on our first flip budget and the number we actually spent were off by about 30 percent. That gap wasn't one big disaster. It was a dozen small things we didn't price in, plus one assumption about timeline that turned out to be wrong. If you're building your first flip budget right now, the honest answer is: whatever you've got written down, add more cushion than feels reasonable, because the categories you're missing are predictable.

Most likely cause: we priced the renovation, not the project

Our budget was basically a materials and labor estimate for the work we could see. New kitchen, new flooring, paint, a bathroom refresh, a roof patch. What we didn't line-item was everything around that work: permits, dumpster rentals, utility costs while the house sat empty, insurance for a vacant property, and the holding costs on the loan or cash tied up every single month the project ran.

This is the most common first-flip mistake, and it's easy to confirm if you've made it too. Pull up your budget spreadsheet. If every line is a trade or a material (plumber, flooring, cabinets, paint) and there's no line for "holding costs" or "permits and fees," you've priced the renovation, not the project. Those soft costs on a typical flip can run 10 to 20 percent of the total budget, sometimes more if the project runs long, and they're the easiest thing to leave off because no contractor quotes them for you.

Less common causes: the mistakes that only show up once you're already in

Beyond missing the big soft-cost categories, there were a few more specific ways our numbers drifted. These are worth checking against your own budget before you start.

How to fix it: building a budget that holds up

If you're putting together your first flip budget now, here's the order we'd do it in, having learned the hard way.

When the numbers mean you shouldn't do the project

Here's the part that's uncomfortable but matters. Sometimes a careful budget tells you the flip doesn't work, and the right move is to walk away or change the plan, not find a way to make the spreadsheet say yes.

A rough rule a lot of experienced flippers use is some version of the 70 percent rule: purchase price plus renovation costs should land at or below about 70 percent of the after-repair value, leaving room for selling costs, holding costs, and profit. It's a rough guide, not gospel, and it varies a lot by market, but if your numbers are coming in at 85 or 90 percent of ARV before you've even hit a surprise, there's no cushion left for the discovery risk every older house carries.

Specific situations where the math usually doesn't work:

We didn't walk away from ours, and it still worked out, but barely, and only because the market moved in our favor during the extra two months. That's not a plan, it's luck. The budgeting mistakes we made are common enough that we wrote them down here at Fixer Files so the next version of us, or you, catches them before the contract is signed instead of after the drywall is up.